The Minister of Power, Engr. Joseph Olasunkanmi Tegbe, has commissioned the upgraded Bauchi 330/132/33kV transmission substation, an intervention expected to improve electricity supply to more than 80,000 households across Bauchi State.
The project, which upgraded the existing 132/33kV facility to a 330/132/33kV transmission substation, is designed to strengthen bulk electricity transmission, improve supply reliability and accommodate future growth in power demand.
Tegbe, who commissioned the facility on Friday in Bauchi on behalf of President Bola Ahmed Tinubu, said the Federal Government was investing in electricity infrastructure to support economic expansion and the President’s ambition of building a $1 trillion economy.
He explained that reliable electricity was essential for business growth, attracting investments, improving public services and creating an enabling environment for economic development.
“Mr President’s aspiration to position Nigeria towards a one trillion dollar economy is therefore aligned with what we’re doing in the electricity sector ,” he said.
The minister disclosed that the substation, which previously had an installed capacity of 112.5MVA, had undergone major upgrades, including the installation of two 150MVA 330/132kV transformers, providing a combined upstream transformation capacity of 300MVA.
At the downstream level, two existing transformers of 22.5MVA and 30MVA were replaced with two 60MVA transformers, while the existing 60MVA unit was retained, bringing the total transformation capacity to 180MVA.
Other components of the project include a modern control room, two 330kV line bays, four 132kV bays, three additional 33kV outgoing feeders and upgraded control and protection facilities.
Tegbe said the intervention would strengthen electricity supply to Bauchi metropolis, Ningi, Dass, Alkaleri and neighbouring communities.
“We are preparing our transmission capacity while we build up our generation capacity, so that we don’t have hiccups when we’re ready to push additional power through the grid,” he said.
He noted that the Federal Government was implementing similar transmission infrastructure upgrades in Lagos, Oyo, Katsina, Kano, Kaduna and Borno states, with further interventions planned for Abia, Edo and Enugu.
The minister also urged residents to protect electricity infrastructure against vandalism, warning that attacks on transmission facilities could disrupt businesses, economic activities and household livelihoods.
“There is no justification for destruction and damage of critical national assets. The cost of vandalism will be felt in interrupted trade, interrupted light, interrupted power, disrupted working hours and disrupted family lives,” he said.
He called on host communities to report suspicious activities around electricity installations and cooperate with relevant authorities to safeguard the facilities.
Tegbe commended the Bauchi State Government, particularly Governor Bala Mohammed, for its cooperation with the Federal Government in facilitating development projects.
He also acknowledged the World Bank’s financial support and the contributions of MBH Power and its consortium partner, Schreder, towards the completion of the project.
Meanwhile, the Managing Director and Chief Executive Officer of the Transmission Company of Nigeria (TCN), Engr. Sule Ahmed Abdulaziz, said the upgrade had increased the facility’s transformation capacity to 300MVA at the 330/132kV level and 180MVA at the 132/33kV level.
He said the development had strengthened bulk power delivery to the Jos Electricity Distribution Company (JEDC), providing additional capacity at the transmission-distribution interface to support electricity distribution across beneficiary communities.
According to Abdulaziz, the communities expected to benefit include Ningi, Dass, Bauchi GRA, Yankari, Nabordo, Dabo Farm and Gubi, with an estimated additional 64,800 beneficiaries.
He explained that the project was awarded in January 2021 and completed in June 2026, adding that it was executed by a joint venture of MBH Power Limited and Shreem Electric Limited with funding from the World Bank.
The TCN managing director said the successful delivery involved extensive engineering works, equipment installation, testing and commissioning.
He appreciated the World Bank, contractors, consultants and TCN engineers who contributed to the completion of the project.