Umahi promises improved connectivity along Lekki corridor, says bridges, drainage, streetlights nearing completion
Commuters, residents and businesses along the Lekki corridor may soon experience some relief from persistent traffic congestion as the Federal Government targets late November to early December 2026 for the commissioning of completed sections of the Lagos-Calabar Coastal Highway.
The planned opening of Sections 1 and 2, covering 100.47 kilometres of dualised concrete carriageway is expected to improve connectivity, ease movement and open up access to residential estates and commercial centres along the rapidly expanding Lekki axis.
Minister of Works, Dave Umahi, gave the assurance yesterday, during an inspection of ongoing construction works on the highway, particularly around Chainage 9+500, near Mayegun and Jakande Estates, Lagos.
He said 47.47 kilometres of Section 1 and 53 kilometres of Section 2 had been completed, bringing the total length of finished carriageway to 100.47 kilometres.
However, the minister explained that the commissioning would initially exclude outstanding bridges and that work was still ongoing on essential road infrastructure, including drainage systems, solar-powered streetlights and other road furniture.
“We are at the final stages, and before the end of December, we shall be completing all the furniture of the road. Sometime this month, November, or early December, we will officially commission the entire Sections 1 and 2, less the bridges,” he said.
For motorists who regularly contend with traffic bottlenecks along the Lekki corridor, the anticipated opening could provide an alternative and more efficient route, although the full benefits will depend on the completion of the supporting infrastructure.
One of the major features inspected by the minister was the first completed flyover and U-turn bridge among the 20 bridges planned for Sections 1 and 2.
Located at Chainage 9+500, the structure is designed to improve traffic circulation by allowing motorists to make U-turns through designated service lanes without disrupting traffic on the main carriageway.
Umahi said construction of the 20 bridges was progressing simultaneously under the Section 2 contract, adding that the coordinated approach was intended to accelerate the delivery of the project.
He commended the contractor, Hitech Construction Company Limited, for delivering more than 200 kilometres of dualised concrete carriageway within two and a half years, describing its construction speed and engineering quality as exceptional.
The minister also disclosed that the Federal Government was concluding selective bidding processes for the construction of service lanes, popularly known as slip roads, and deep drainage channels to discharge stormwater into the lagoon.
He said the facilities were essential to the highway’s functionality, particularly during heavy rainfall, while ensuring better access to communities and businesses along the corridor.
On the asphalt recently laid on the completed concrete bridge, Umahi explained that the overlay was consistent with international engineering standards.
According to him, the asphalt finish would enhance the appearance of the bridge and facilitate the installation of expansion joints, which allow the structure to accommodate movement caused by temperature changes and other engineering factors.
He added that the adoption of continuously reinforced concrete pavement (CRCP) and solar-powered streetlights could also position the project to qualify for international carbon credit claims.
Beyond the coastal highway, Umahi provided updates on other federal road projects across the country and acknowledged the hardship motorists had experienced because of ongoing construction.
On the Lagos-Ibadan Expressway, he apologised to commuters over recent traffic gridlock caused by a contractor blocking a carriageway to install an overhead bridge.
He said he had directed that such installations should henceforth be carried out only on Sundays, beginning from midnight, to minimise disruption and reduce the inconvenience to road users.
On the Benin-Asaba corridor, the minister said Hitech had been engaged to undertake permanent palliative works, with asphalt already laid on 40 kilometres of the Benin axis.
He added that procurement for the full reconstruction of the corridor was ongoing.
For the East-West Road, Umahi said the Federal Government was pursuing procurement under an Engineering, Procurement, Construction and Financing (EPC+F) arrangement for the dualisation of the 67-kilometre Edo section, through the Benin Bypass, and the 104-kilometre Delta section.
The projects form part of the broader 400-kilometre road corridor linking Benin and Calabar.
He also reported progress on other major highway projects, including the 1,068-kilometre Sokoto-Badagry Highway, which he said was more than 30 per cent completed, and the 465-kilometre Trans-Saharan Highway, with approximately 20 per cent completion.
Construction is also ongoing on the Akwanga-Jos-Bauchi-Gombe-Biu-Maiduguri highway corridor.