‘Stadium still being renovated’
Contrary to some media reports, the Delta State government, yesterday, declared that the re-modelled Warri City stadium has not been completed and is not ready for commissioning.
The declaration came following reports that FIFA President Gianni Infantino and CAF President Patrice Motsepe are expected in Warri this Saturday, November 21, to, among other things, commission the reconstructed Warri City Stadium.
Delta State Governor, Sheriff Oborevwori, insisted yesterday that the 15,000-capacity Warri City Stadium must be 100 per cent completed before commissioning.
The governor’s clarification came just as an official of the Delta Sports Commission told The Guardian yesterday that no top official of the Commission is aware of the visit by Infantino and Motsepe to the stadium complex.
“We only heard from outsiders that FIFA President Gianni Infantino and CAF President Patrice Motsepe are coming to commission Warri Stadium on Saturday,” the official said.
“There was no official communication with the Chairman of the Sports Commission, Onoriode Oborevwori, nor other top officials of the Commission.
“We are surprised to read about the stadium commissioning. Indeed, things are not done that way. We know very well that Warri stadium has not been completed. This present governor doesn’t commission projects that are not 100 per cent completed. People should learn to respect and follow official protocols,” the angry official said.
The Guardian learnt that the news of the visit by Infantino and Motsepe to Warri Stadium prompted Governor Oborevwori to dispatch the Commissioner for Works (Rural Roads) and Public Information, Charles Aniagwu, to the complex on Tuesday evening.
After his inspection of Warri Stadium, Aniagwu said the complex is not ready for commissioning this Saturday, as reported by some media outfits, but noted that work on the rehabilitation and upgrade of the facility was near completion.
He expressed satisfaction with the quality of work while stressing the governor’s determination to ensure that the facility meets the required standards.
Aniagwu, who led the inspection of the main stadium bowl, swimming pool arena, VIP lounges, media centre, dressing rooms for home and visiting teams, and other supporting facilities, said the state government would not compromise on quality in its determination to restore the stadium to its former glory.
He explained that the inspection was part of the government’s commitment to ensuring that every component of the project was delivered according to specifications, adding that a few areas requiring attention had been identified and communicated to the contractor and consultant.
The commissioner added that the stadium had been designed to provide spectators with unobstructed views of activities on the pitch from virtually every section of the stands.
He said the ongoing rehabilitation extended beyond the main bowl to include the training pitch and facilities for indoor sporting activities, noting that considerable work had gone into restoring the entire complex.
The Guardian learnt yesterday that some of the facilities, including the solar power system, practice pitch seats for the indoor hall and swimming pool, as well as the indoor floor, are yet to be completed.